Serial number
|
Work Objectives
|
Work tasks
|
Responsible Unit
|
Schedule
|
|
1
|
Ascertain the baseline data.
|
Establish ledgers and inventories for industrial parks and enterprises.
|
All municipal governments
Xiong’an New Area Administrative Committee
Provincial Emergency Management Department
|
4 month 30 Recently, completed “ One enterprise, one file. ”“ One garden, one file. ” And report it.
|
|
2
|
Assessment Classification
|
Develop evaluation criteria
|
Provincial Emergency Management Department
Provincial Department of Transport
Provincial Department of Ecology and Environment
|
4 month 15 Recently, standardized management assessment criteria for chemical enterprises, hazardous‑goods transportation companies, and hazardous‑waste disposal and utilization facilities across the province were formulated and submitted to the Provincial Task Force Office for promulgation.
|
|
Conduct an assessment
|
All municipal governments
Xiong’an New Area Administrative Committee
Provincial Emergency Management Department
|
4 month 20 Recently, an implementation plan for the assessment has been formulated.
5 month 31 Recently, reported to “ Four batches ” List of enterprises.
6 month 1 Effective from today, newly established chemical production projects shall undergo timely assessments, have their records updated, and be reported without delay.
|
|
3
|
Implementation
“ Four batches ”
|
Shut down and ban a batch of…
|
All municipal governments
Xiong’an New Area Administrative Committee
Provincial Emergency Management Department
|
6 month 30 Recently, production shutdown plans have been formulated and evaluated on a case-by-case basis.
7 month 31 Recently, all enterprises have completed safe shutdowns and submitted their lists of suspended operations.
8 month 31 Recently, the material disposal has been completed.
9 month 30 Recently, demolition plans have been drawn up for each enterprise, and the demolition process has been initiated.
10 month 31 Recently, equipment and facilities in critical (hazardous) areas, as well as hazardous installations, have been dismantled.
11 month 30 Recently, all cities have completed on-site inspections of demolition enterprises and submitted their inspection reports. The Provincial Task Force has organized unannounced spot checks.
|
|
3
|
Implementation
“ Four batches ”
|
A batch of enterprises has relocated to the industrial park.
|
All municipal governments
Provincial Department of Industry and Information Technology
Provincial Emergency Management Department
|
6 month 30 Recently, the rectification of potential hazards has been completed, and the results have been reported through the Hebei Province Hazard Identification and Remediation Information System.
9 month 30 Recently, apart from those designated by the provincial government, 39 For enterprises that, following investigation, assessment, and verification, meet the criteria for relocation, a tailored relocation and renovation plan shall be developed on a case-by-case basis, and the corresponding list shall be submitted to the Provincial Department of Industry and Information Technology.
10 month 31 Recently, the provincial government has determined… 39 All enterprises have completed relocation and renovation.
11 month 30 Recently, the relevant cities have… 39 On-site acceptance inspections are conducted for each enterprise regarding relocation and renovation, with the inspection results reported to the Provincial Department of Industry and Information Technology.
12 month 31 Recently, the Provincial Department of Industry and Information Technology conducted supervisory inspections to assess the progress of relocation and renovation projects in all cities.
|
|
Renovate and upgrade a batch of…
|
All municipal governments
Provincial Emergency Management Department
|
6 month 30 Recently, the rectification of potential hazards has been completed, and the results have been reported through the Hebei Province Hazard Identification and Remediation Information System.
7 month 31 Recently, tailored renovation and upgrading plans have been developed for each enterprise.
10 month 31 Recently, completed 50% The automation control system upgrades for manufacturing enterprises have been reported, and the list of completed projects has been submitted. For enterprises that have suspended production, upgrades must be carried out first before resuming operations.
12 month 31 Recently, the manufacturing enterprise 100% The upgrade of the automated control system has been completed, and the list of completed projects has been submitted. Enterprises that have suspended production will undergo the upgrade first before resuming operations.
|
|
Strengthen and optimize a group of…
|
All municipal governments
Provincial Emergency Management Department
|
6 month 30 Recently, the rectification of potential hazards has been completed, and the results have been reported through the Hebei Province Hazard Identification and Remediation Information System.
9 month 30 Recently, cities have formulated tailored plans to strengthen and optimize individual enterprises and submitted them for approval.
12 month 31 Recently, cities have identified and submitted lists of demonstration enterprises to be strengthened and upgraded.
|
|
4
|
Raise the entry threshold
|
Strict industry access requirements
|
Provincial Development and Reform Commission
Provincial Department of Industry and Information Technology
Provincial Department of Ecology and Environment
Provincial Department of Natural Resources
Provincial Emergency Management Department
Provincial Department of Housing and Urban-Rural Development
Provincial Department of Transport
|
4 Starting from [month], all municipal-level emergency management departments shall submit, on a monthly basis, the local statistical report on chemical (hazardous chemicals) construction projects, including details of safety oversight and verification by emergency management personnel during the trial production and completion acceptance phases.
5 month 31 Recently, the Provincial Safety Committee Office took the lead in formulating measures involving… “ Two priorities and one major issue ” Measures for the Joint Review of Chemical Engineering Construction Projects.
6 month 1 Effective from this date, with respect to matters involving “ Two priorities and one major issue ” Construction projects shall, following a joint review conducted under the leadership of the safety committee office at or above the municipal level and involving relevant departments, be approved in accordance with the applicable administrative authority. The results of each review shall be promptly reported.
|
|
4
|
Raise the entry threshold
|
Strict administrative licensing
|
Provincial Emergency Management Department
Provincial Department of Transport
|
3 month 5 Effective from today, the licensing of road transport enterprises for hazardous chemicals (hazardous goods) is suspended.
4 month 1 Effective from this date, all cities shall submit monthly reports on the entrusted processing of safety production licenses for hazardous chemical production enterprises, including enterprise names, expert panel compositions, and review opinions.
|
|
5
|
Strict park management
|
Manage and control risks in the park.
|
All municipal governments
Provincial Emergency Management Department
|
4 month 30 Recently, cities have completed regional safety assessments of their local chemical industrial parks (or conducted reviews of such assessments), comprehensively evaluating the parks’ safety risk capacity, enterprise layout, and surrounding hazards. They are also urging that potential risks of spillover from within the parks be addressed. “ Domino ” Enterprises subject to the effect shall implement risk prevention and control measures and report on evaluation results and follow-up review outcomes.
5 month 31 Recently, for labor-intensive non-chemical enterprises within the park that do not align with its functional positioning, specific relocation deadlines have been set, relocation measures have been formulated, and these have been submitted for approval.
6 month 30 Recently, the plan for relocating villages, schools, and other facilities located within the park’s perimeter that fail to meet the required safety buffer distances has been finalized and submitted for approval, and relocation work has now been initiated.
12 month 31 Recently, the relocation of labor-intensive non-chemical enterprises within the park that no longer align with its functional positioning has been completed, and the results have been reported.
|
|
Strengthen information technology development
|
All municipal governments
Provincial Emergency Management Department
|
4 month 30 Recently, the chemical industrial park has developed an information platform for interfacing with all enterprises (with… Security Situation Develop and submit a construction plan with a focus on anomaly alarms, major hazard sources, high-risk process facilities, and online monitoring and surveillance of hazardous chemical storage tanks.
5 month 31 Recently, the formulation outside the park “ Two priorities and one major issue ” Enterprise-related monitoring data (based on Security Situation Implementation plan for connecting abnormality alarms—focusing on major hazard sources, high-risk process facilities, and online monitoring and surveillance of hazardous chemical storage tanks—to the provincial, municipal, and county-level work safety supervision platforms.
6 month 30 Recently, the completion rate of information platforms in chemical industrial parks across various cities has reached 50% , submit the name of the park and the list of participating enterprises.
8 month 31 Recently, all chemical industrial parks across the cities have completed the construction of their information platforms and submitted reports detailing the park names and the list of connected enterprises.
10 month 31 Recently, areas outside the chemical industrial parks in various cities have been involved… “ Two priorities and one major issue ” All enterprise monitoring data have been integrated into the provincial, municipal, and county-level work safety supervision platforms, and the list of reporting-compliant enterprises has been submitted.
|
|
6
|
Strengthen safety management and control at key links and critical areas.
|
Strengthen safety supervision of hot work operations.
|
Provincial Emergency Management Department
|
4 month 1 Effective from today, hot work operations shall be implemented. “ Monthly Report ” Management: For chemical enterprises handling hazardous chemicals, Class I and Class II hot work operations must be reported to the municipal emergency management authority, while Class III hot work operations must be reported to the county-level emergency management authority. Hot work is strictly prohibited unless it is conducted under the full‑time supervision of experts organized by the emergency management authority or by a safety technical service agency engaged by the enterprise.
Each city shall submit a monthly report on the review of Class I hot work operations.
|
|
Strengthen safety oversight of vehicle entry and exit.
|
Provincial Emergency Management Department
|
4 month 1 Effective from today, parking will be permitted. “ Monthly Report ” Management: Each city shall submit a monthly report on the review of production shutdowns and resumptions by the end of each month.
|
|
Strengthen safety supervision of outsourced construction work.
|
Provincial Emergency Management Department
|
4 month 1 Effective from today, outsourced construction will be implemented. “ Monthly Report ” Management: Each city shall submit a monthly report on the review status of outsourced construction contractors by the end of each month.
|
|
Strengthen the supervision and management of special equipment.
|
Provincial Market Supervision Administration
|
4 month 30 Recently, market supervision authorities at all levels have conducted a comprehensive survey of in-service special equipment at chemical enterprises across the province, establishing a registry of such equipment. “ One enterprise, one file. ”。
5 month 31 Recently, market supervision authorities across various localities have conducted thorough legal and compliance reviews of special‑purpose equipment at chemical enterprises within their jurisdictions, comprehensively identifying and addressing safety hazards associated with such equipment, and recording the findings in official files. Following signature and confirmation by the principal leaders of the relevant counties (or urban districts), the reports have been submitted to the provincial market supervision bureau.
7 month 31 Recently, all cities have completed the rectification of identified problems and potential hazards. The progress of these rectifications has been reported to the Provincial Market Supervision Administration.
|
|
Strengthen safety management and control of hazardous chemical transportation.
|
Provincial Department of Transport
|
4 month 30 Recently, transportation authorities at all levels have conducted a comprehensive baseline survey of hazardous chemical (hazardous goods) transport enterprises across the province and established… “ One enterprise, one file. ”。
5 month 31 Recently, transportation authorities across various regions have conducted individual legal and compliance reviews of hazardous chemical (hazardous goods) transport enterprises within their jurisdictions, thoroughly identified and addressed safety hazards, and documented the findings in official records. Following signature and confirmation by the principal leaders of the relevant counties (districts or municipal districts), these reports have been submitted to the provincial Department of Transport.
7 month 31 Recently, the rectification of identified issues and potential hazards has been completed, and the progress report has been submitted to the Provincial Department of Transport.
|
|
Strengthen the management of the disposal of discarded hazardous chemicals.
|
Provincial Department of Ecology and Environment
|
4 month 30 Recently, ecological and environmental authorities at all levels have conducted a comprehensive baseline survey of hazardous waste management and disposal enterprises across the province, establishing… “ One enterprise, one file. ”。
5 month 31 Recently, ecological and environmental authorities across various regions have conducted item-by-item reviews of the legal and regulatory compliance of hazardous waste management and disposal enterprises within their jurisdictions, thoroughly identified and addressed safety hazards, and documented the findings in official records. Following signature and confirmation by the principal leaders of the relevant counties (or urban districts), these reports have been submitted to the provincial Department of Ecology and Environment.
7 month 31 Recently, the rectification of identified issues and potential hazards has been completed. The progress of the rectification has been reported to the Provincial Department of Ecology and Environment.
|
|
7
|
Strictly enforce the principal responsibility of enterprises for workplace safety.
|
Strengthen the capacity of principal persons in charge to perform their duties in accordance with the law.
|
Provincial Emergency Management Department
|
3 month 31 Recently, the development of an examination question bank for principal persons in charge of hazardous chemical production enterprises has been completed.
4 month 1 Effective from today, the principal person in charge of hazardous chemical production enterprises shall be subject to… “ A mandatory exam for every license. ”。
754 for the entire year The principal persons in charge of domestic hazardous chemical production enterprises shall take a closed-book examination on their job competency in four phases.
5 month 31 Recently, the first round of performance evaluations for key leaders has been completed.
7 month 31 Recently, the assessment of the second batch of principal officials was completed.
9 month 30 Recently, the assessment of the third batch of principal officials was completed.
11 month 30 Recently, the fourth round of performance evaluations for key executives was completed.
|
|
Improve the safety production management system.
|
Provincial Emergency Management Department
|
4 month 30 Recently, all cities have conducted a comprehensive survey of the status of safety directors (chief safety officers), the establishment of safety management organizations, and the staffing of full-time safety management personnel at all chemical (hazardous chemicals) enterprises within their jurisdictions, and have established… “ One enterprise, one file. ”。
5 month 31 Recently, the establishment of a Chief Safety Officer, the creation of a dedicated safety management organization, and the staffing of full-time safety management personnel have been completed. A detailed list has been submitted, reporting the number of enterprises that have appointed a Chief Safety Officer, established dedicated safety management bodies, and deployed full-time safety management personnel.
|
|
Significantly enhance the level of automated control.
|
Provincial Emergency Management Department
Provincial Market Supervision Administration
|
8 month 31 Recently, county-level emergency management departments, in coordination with market supervision authorities and in accordance with their respective responsibilities, have urged enterprises to complete the assessment and inspection of aging equipment and facilities. Equipment that, following such assessments, is found to have reached its designed service life or meets relevant scrapping criteria must be phased out and replaced, with a detailed list of these decommissioning activities submitted for reporting.
|
|
8
|
Safeguard measures
|
Strengthen organizational leadership
|
Governments of all cities and counties
|
4 month 15 Recently, cities have formulated local action plans to tackle key challenges, convened special mobilization and deployment meetings, established leading groups and offices for the campaign to improve workplace safety in the chemical industry, and put in place corresponding working mechanisms before submitting them for approval.
|